PMP: Scope Management : Control Scope Output
Control Scope Output
List of Control Scope Output
-
Work Performance Information
-
Change Requests
-
Project Management Plan Updates
-
Project Documents Updates
-
Organizational Process Assets Updates
Project sponsors have the GREATEST influence on the scope, quality, time, and cost of the project during the:
-
a) Concept phase.
-
b) Development phase.
-
c) Execution phase.
-
d) Close-down phase.
Answer: Concept phase.
A scope statement is important because it:
-
a) Provides the basis for making future project decisions.
-
b) Provides a brief summary of the project.
-
c) Approves the project for the stakeholders.
-
d) Provides criteria for measuring project cost.
Answer: Provides the basis for making future project decisions.
| Question: hat is the FIRST step to take as you begin planning? |
| A. Identify the risks. |
| B. Plan the scope. |
| C. Establish a resource plan. |
| D. Complete a cost and schedule estimate. |
|
Answer: 2
|
Answer explanation:
Scope Management
|
| Question: Effective stakeholder management includes all of the following project elements EXCEPT: |
| A. Clear requirements definition. |
| B. Scope change control. |
| C. Timely status information. |
| D. Frequent cost reports. |
|
Answer: 4
|
Answer explanation:
Scope Management
|
| Question: A likely result of using "compromise" to resolve a two-party conflict is: |
| A. Lose-lose. |
| B. Win-lose. |
| C. Win-win. |
| D. Lose-win. |
|
Answer: 1
|
Answer explanation:
Scope Management
|
| Question: As part of the quality audit, the scope statement is checked against the work results to ensure the conformance to the customer requirements. The results should be documented and used for: |
| A. Estimating future projects. |
| B. Changing the project scope. |
| C. Defining future project tasks. |
| D. Validating the quality process. |
|
Answer: 3
|
Answer explanation:
Scope Management
|
| Question: A generally accepted method to confirm accuracy of task progress is through: |
| A. Earned value. |
| B. Probability vs. outcome. |
| C. Maximum ceiling. |
| D. Work breakdown structure. |
|
Answer: 1
|
Answer explanation:
Scope Management
|
| Question: Which of the following techniques is used to control the project schedule? |
| A. Pareto diagram |
| B. Performance measurement |
| C. Parametric modeling |
| D. Statistical sampling |
|
Answer: 2
|
Answer explanation:
Scope Management
|