PMP: Scope Management : Collect Requirement Output
What are the Outputs of Collect Requirements in project scope management?
The Outputs of Collect Requirements in project scope management:
What the requirement document contains?
The requirement document contains
| Question: Effective stakeholder management includes all of the following project elements EXCEPT: |
| A. Clear requirements definition. |
| B. Scope change control. |
| C. Timely status information. |
| D. Frequent cost reports. |
|
Answer: 4
|
Answer explanation:
Scope Management
|
| Question: A likely result of using "compromise" to resolve a two-party conflict is: |
| A. Lose-lose. |
| B. Win-lose. |
| C. Win-win. |
| D. Lose-win. |
|
Answer: 1
|
Answer explanation:
Scope Management
|
| Question: As part of the quality audit, the scope statement is checked against the work results to ensure the conformance to the customer requirements. The results should be documented and used for: |
| A. Estimating future projects. |
| B. Changing the project scope. |
| C. Defining future project tasks. |
| D. Validating the quality process. |
|
Answer: 3
|
Answer explanation:
Scope Management
|
| Question: A generally accepted method to confirm accuracy of task progress is through: |
| A. Earned value. |
| B. Probability vs. outcome. |
| C. Maximum ceiling. |
| D. Work breakdown structure. |
|
Answer: 1
|
Answer explanation:
Scope Management
|
| Question: Which of the following techniques is used to control the project schedule? |
| A. Pareto diagram |
| B. Performance measurement |
| C. Parametric modeling |
| D. Statistical sampling |
|
Answer: 2
|
Answer explanation:
Scope Management
|
| Question: You are in charge of developing a new product for a bank. Your quality metrics are based on the 80th percentile of each of the last three products developed, This is an example of: |
| A. Statistical sampling |
| B. Metrics |
| C. Benchmarking |
| D. Operational definitions |
|
Answer: 3
|
Answer explanation:
Scope Management
|