Question No: 1
In a textile manufacturing project, a team divided the whole project work into 35 work packages and assigned a few work packages to the design department for review. After reviewing, the manager of the design department has recently requested the team to further divide the work packages into more manageable work components for estimating and scheduling the resources. In this scenario, which of the following techniques should the team use to complete the manager's request?



 