Learn and Practice Free Total PMP Set 7 questions

Click below to Practice Free Total PMP Set 7 Questions


You can get answer of the below sample questions by going through the above Question sets.


The MAJOR processes for project integration management are:


Option 1: Project plan development, project plan execution, and overall change control.
Option 2: Project plan development, project plan execution, and scope change control.
Option 3: Project plan development, overall change control, and scope change control.
Option 4: Project plan development, initiation, and overall change control.
Option 5:


The major difference(s) between time-limited scheduling and resource leveling is (are):


Option 1: Time-limited scheduling reschedules based on late start dates, while resource leveling reschedules based on late finish dates.
Option 2: Time-limited scheduling considers total float but resource leveling does not.
Option 3: Time-limited scheduling reschedules activities according to resource availability while resource leveling attempts to smooth resource requirements by rescheduling.
Option 4: A and C
Option 5: All of the above


The first phase of your project has come to an final. What should you ensure is done BEFORE beginning the next phase?


Option 1: Verify that the resources are available for the next phase
Option 2: Check the project's progress compared to its baselines
Option 3: Confirm that the phase has reached its objectives and formally accept its deliverables
Option 4: Take corrective action to bring project results in line with project expectations
Option 5:


The one document that should always be used to help identify risk is the:


Option 1: Risk Management Plan
Option 2: WBS
Option 3: Scope Statement
Option 4: Project Charter
Option 5: Contigency Plan


The contract type that represents the lowest risk to the buyer is:


Option 1: CPIF
Option 2: FPI
Option 3: FFP
Option 4: CPFF
Option 5: CPPC


The contract type that represents the greatest risk to the buyer is:


Option 1: CPIF
Option 2: FPI
Option 3: FFP
Option 4: CPFF
Option 5: CPPC


The "rule of seven" as applied to process control charts means that


Option 1: Seven rejects typically occur per thousand inspections.
Option 2: Seven consecutive points are ascending, descending, or the same.
Option 3: At least seven inspectors should be in place for every thousand
Option 4:
Option 5:


The lowest level of the WBS is referred to as the ______________, especially in organizations that follow earned value management practices:


Option 1: Control account
Option 2: Code of accounts
Option 3: Summary level task
Option 4: Work Package
Option 5: Deliverable


The major processes in project integration management are:


Option 1: Guide project execution, document project planning assumptions, facilitate communication
Option 2: Inputs, Tools and Techniques, Outputs
Option 3: Project plan development, project plan execution, integrated change control
Option 4: General management, product knowledge, project management information
Option 5: Product knowledge, project execution, facilitate communication


The closing process scope includes:


Option 1: Contract closeout
Option 2: Final reporting
Option 3: Punchlist
Option 4: Exit interview
Option 5: Lessons learned


The core planning processes are:


Option 1: Scope definition, Resource planning, Cost estimating, Schedule development, Activity definition
Option 2: Inputs, Control, Status reports, Risk management
Option 3: Planning, Resource planning, Quality assurance, Risk control
Option 4: Cope definition, Team development, Schedule control, Budget control, Contract administration
Option 5: Quality planning, Communication planning, Staff acquisition,, Risk quantification


The amount of time that an activity can be delayed from its early start without delaying the project end date is called:


Option 1: Negative Float
Option 2: Free Float
Option 3: Total Float
Option 4: Float
Option 5: c and d


The most important document to help a project manager control the project is the:


Option 1: Contract specification
Option 2: Work breakdown structure
Option 3: Project requirements document
Option 4: Risk assessment
Option 5: Cost-benefit ratio


The Critical Path Method of scheduling is:


Option 1: A technique used to predict project duration by analyzing which sequence of activities has the least amount of float
Option 2: A technique that uses weighted averages to calculate project duration
Option 3: A technique that uses sequential network logic for schedule development
Option 4: A technique that allows for probabilistic treatment of both network logic and activity duration estimates
Option 5: All of the above


The decomposition process is a technique used to construct a:


Option 1: Precedence network.
Option 2: Critical Path Method Diagram.
Option 3: Variance analysis.
Option 4: Work breakdown structure.
Option 5:

Practice Free Total PMP Set 7 Questions online

By Practicing the below question set :
The student will get the basic and advanced knowledge on Total PMP Set 7.
The student will learned the priciples and methedology of Total PMP Set 7.
The student will evaluate the knowledge level on Total PMP Set 7.
Student can practice number of times the question till he is clear.
Student can provide the review / feedback / suggestion on the questions which will help to others.
The question contains the simple to complex level difficulties so that student can improve the knowledge.


Kindly Note : The information provided here is just indicative information and is provided on “as is” and “as available” basis . We make no claims on accuracy and reliability of the information. For correct/current information kindly contact concerned college/institution/authorities

Advertisements
Advertisements

Mail: Support@gicgac.com