Learn and Practice Free Total PMP Set 7 questions	
                    
                    
Click below to Practice Free Total PMP Set 7 Questions
                     
                        
                    
                    
You can get answer of the below sample questions by going through the above Question sets. 
                    
The MAJOR processes for project integration management are:
 Option 1:  Project plan development, project plan execution, and overall change control.
 Option 2:  Project plan development, project plan execution, and scope change control.
 Option 3:  Project plan development, overall change control, and scope change control.
 Option 4:  Project plan development, initiation, and overall change control.
 Option 5: 
The major difference(s) between time-limited scheduling and resource leveling is (are):
 Option 1:  Time-limited scheduling reschedules based on late start dates, while resource leveling reschedules based on late finish dates.
 Option 2:  Time-limited scheduling considers total float but resource leveling does not.
 Option 3:  Time-limited scheduling reschedules activities according to resource availability while resource leveling attempts to smooth resource requirements by rescheduling.
 Option 4:  A and C
 Option 5:  All of the above
The first phase of your project has come to an final.  What should you ensure is done BEFORE beginning the next phase?
 Option 1:  Verify that the resources are available for the next phase
 Option 2:  Check the project's progress compared to its baselines
 Option 3:  Confirm that the phase has reached its objectives and formally accept its deliverables
 Option 4:  Take corrective action to bring project results in line with project expectations
 Option 5: 
The one document that should always be used to help identify risk is the:
 Option 1:  Risk Management Plan
 Option 2:  WBS
 Option 3:  Scope Statement
 Option 4:  Project Charter
 Option 5:  Contigency Plan
The contract type that represents the lowest risk to the buyer is: 
 Option 1:  CPIF
 Option 2:  FPI
 Option 3:  FFP
 Option 4:  CPFF
 Option 5:  CPPC
The contract type that represents the greatest risk to the buyer is: 
 Option 1:  CPIF
 Option 2:  FPI
 Option 3:  FFP
 Option 4:  CPFF
 Option 5:  CPPC
The "rule of seven" as applied to process control charts means that
 Option 1:  Seven rejects typically occur per thousand inspections.
 Option 2:  Seven consecutive points are ascending, descending, or the same.
 Option 3:  At least seven inspectors should be in place for every thousand 
 Option 4: 
 Option 5: 
The lowest level of the WBS is referred to as the ______________, especially in organizations that follow earned value management practices: 
 Option 1:  Control account
 Option 2:  Code of accounts
 Option 3:  Summary level task
 Option 4:  Work Package
 Option 5:  Deliverable
The major processes in project integration management are: 
 Option 1:  Guide project execution, document project planning assumptions, facilitate communication
 Option 2:  Inputs, Tools and Techniques, Outputs
 Option 3:  Project plan development, project plan execution, integrated change control
 Option 4:  General management, product knowledge, project management information
 Option 5:  Product knowledge, project execution, facilitate communication
The closing process scope includes: 
 Option 1:  Contract closeout
 Option 2:  Final reporting
 Option 3:  Punchlist
 Option 4:  Exit interview
 Option 5:  Lessons learned
The core planning processes are: 
 Option 1:  Scope definition, Resource planning, Cost estimating, Schedule development, Activity definition
 Option 2:  Inputs, Control, Status reports, Risk management
 Option 3:  Planning, Resource planning, Quality assurance, Risk control
 Option 4:  Cope definition, Team development, Schedule control, Budget control, Contract administration
 Option 5:  Quality planning, Communication planning, Staff acquisition,, Risk quantification
The amount of time that an activity can be delayed from its early start without delaying the project end date is called: 
 Option 1:  Negative Float 
 Option 2:  Free Float 
 Option 3:  Total Float 
 Option 4:  Float 
 Option 5:  c and d
The most important document to help a project manager control the project is the:
 Option 1:  Contract specification
 Option 2:  Work breakdown structure
 Option 3:  Project requirements document
 Option 4:  Risk assessment
 Option 5:  Cost-benefit ratio
The Critical Path Method of scheduling is: 
 Option 1:  A technique used to predict project duration by analyzing which sequence of activities has the least amount of float
 Option 2:  A technique that uses weighted averages to calculate project duration
 Option 3:  A technique that uses sequential network logic for schedule development
 Option 4:  A technique that allows for probabilistic treatment of both network logic and activity duration estimates
 Option 5:  All of the above
The decomposition process is a technique used to construct a:
 Option 1:  Precedence network.
 Option 2:  Critical Path Method Diagram.
 Option 3:  Variance analysis.
 Option 4:  Work breakdown structure.
 Option 5: 
Practice Free Total PMP Set 7 Questions online
                    
By Practicing the below question set :
The student will get the basic and advanced knowledge on  Total PMP Set 7.
The student will learned the priciples and methedology of  Total PMP Set 7.
The student will evaluate the knowledge level on Total PMP Set 7.
Student can practice number of times the question till he is clear.
 Student can provide the review / feedback / suggestion on the questions which will help to others.
 The question contains the simple to complex level difficulties so that student can improve the knowledge.
                    
                    
	 
                        Kindly 
                              Note : The information provided here is just indicative 
                              information and is provided on “as is” 
                              and “as available” basis . We make no 
                              claims on accuracy and reliability of the information. 
                              For correct/current information kindly contact concerned 
                              college/institution/authorities