Learn and Practice Free Integration Management Set 2 questions

Click below to Practice Free Integration Management Set 2 Questions


You can get answer of the below sample questions by going through the above Question sets.


The two closing procedures are called:


Option 1: Contract close out and scope verification
Option 2: Contract close out and administrative closure
Option 3: Project closure and product verification
Option 4: Project closure and lessons learned
Option 5:


Scoring models, comparative approaches and benefit contribution are all part of:


Option 1: Constrained optimization models for selecting a project
Option 2: Benefit measurement models for selecting a project
Option 3: Quality measurement techniques
Option 4: Information distribution tools
Option 5:


Which of the following is a common characteristic of most project life cycle descriptions?


Option 1: Cost and staffing are low at the start, higher towards the end, and drop rapidly as the project nears completion.
Option 2: The probability of successfully completing the project is highest at the start of the project.
Option 3: Stakeholders have the most influence on the final characteristics of the product at the end of the project.
Option 4: a and b
Option 5:


The major processes in project integration management are:


Option 1: Guide project execution, document project planning assumptions, facilitate communication
Option 2: Inputs, Tools and Techniques, Outputs
Option 3: Project plan development, project plan execution, integrated change control
Option 4: General management, product knowledge, project management information
Option 5: Product knowledge, project execution, facilitate communication


Tools and Techniques for project plan development include:


Option 1: Project planning methodology, stakeholders skills and knowledge, project management information system (PMIS)
Option 2: General management skills, project management information systems
Option 3: Organizational procedures
Option 4: Work authorization systems, status review meetings
Option 5: All of the above


Status review meetings are:


Option 1: Held to notify stakeholders of critical information
Option 2: Regularly scheduled meetings held to exchange information about the project
Option 3: Held to update departmental staff of project status
Option 4: Held only when there is an identified problem
Option 5: None of the above


____________ is any documented procedure used to apply technical and administrative direction and surveillance to identify control and record any changes to product characteristics.


Option 1: Scope Change Control
Option 2: Schedule Change Control
Option 3: Quality Control
Option 4: Configuration Management
Option 5: Contract Administration


The project planning methodology is defined in the PMBOK as:


Option 1: Using planning techniques to achieve a desired end goal
Option 2: A structured approach used to guide a project team during development of a project plan
Option 3: Organizational policies
Option 4: General management skills
Option 5: All of the above


A ______________ consists of the tools and techniques used to gather, integrate, and disseminate the outputs of the other project management processes.


Option 1: Project management planning system
Option 2: Project controls system
Option 3: Project communication system
Option 4: Project management information system
Option 5: Project organizational policies


Supporting detail for the project plan includes:


Option 1: Outputs from other planning processes
Option 2: Information/documentation generated during development of the project plan
Option 3: Technical documentation
Option 4: Documentation of relevant standards
Option 5: All of the above


The project plan is used to:


Option 1: Provide project inputs, tools and techniques, and outputs
Option 2: Guide project execution, document project planning assumptions, and facilitate communication among stakeholders
Option 3: Provide general management, product knowledge, and project management information
Option 4: Create organized policies using stakeholders skills and knowledge
Option 5: All of the above


_____________ are the outcomes of the activities performed to accomplish the project.


Option 1: Change request
Option 2: Performance reports
Option 3: Work results
Option 4: Additional planning
Option 5: Corrective action


Assumptions generally involve:


Option 1: A degree of risk
Option 2: Involvement from stakeholders
Option 3: Financial controls
Option 4: Historical information
Option 5: Lessons Learned


______________ are applicable restrictions that will affect project performance


Option 1: Organizational policies
Option 2: Performance guidelines
Option 3: Constraints
Option 4: Additional planning requirements
Option 5: None of the above


_______________ is a formal, approved document used to manage and control project execution


Option 1: Project plan
Option 2: Organizational policies
Option 3: Organizational procedures
Option 4: Work authorization system
Option 5: Configuration management

Practice Free Integration Management Set 2 Questions online

By Practicing the below question set :
The student will get the basic and advanced knowledge on Integration Management Set 2.
The student will learned the priciples and methedology of Integration Management Set 2.
The student will evaluate the knowledge level on Integration Management Set 2.
Student can practice number of times the question till he is clear.
Student can provide the review / feedback / suggestion on the questions which will help to others.
The question contains the simple to complex level difficulties so that student can improve the knowledge.


Kindly Note : The information provided here is just indicative information and is provided on “as is” and “as available” basis . We make no claims on accuracy and reliability of the information. For correct/current information kindly contact concerned college/institution/authorities

Advertisements
Advertisements

Mail: Support@gicgac.com