Learn and Practice Free Cost Management Set 1 questions

Click below to Practice Free Cost Management Set 1 Questions


You can get answer of the below sample questions by going through the above Question sets.


The three most common types of project cost estimates are:


Option 1: Order of magnitude, parametric and budget
Option 2: Parametric, definitive, and analogous
Option 3: Order of magnitude, budget, and definitive
Option 4: Analogous, parametric, and bottom-up
Option 5: Order of magnitude, definitive, and bottom-up


A definitive estimate should give the manager cost data accurate to within:


Option 1: -5 to +10 percent of actual costs
Option 2: -25 to +75 percent of actual costs
Option 3: -30 to +85 percent of actual costs
Option 4: -10 to +25 percent of actual costs
Option 5: None of the above


A graphical display of accumulated costs and labor hours for both budgeted and actual cost, plotted against time, is called a(n) ______________.


Option 1: Trend line
Option 2: Trend analysis
Option 3: Cost baseline
Option 4: Percent completion report
Option 5: Earned value report


Which of the following depreciation methods provides for accelerated depreciation of an asset:


Option 1: Double-declining balance
Option 2: Straight line
Option 3: Exponential depreciation
Option 4: Double sum-of-the-year digits
Option 5: Double increasing balance


Cost performance index is:


Option 1: AC/EV
Option 2: SPI/PV
Option 3: EV/AC
Option 4: PV/EV
Option 5: None of the above


The future value of $ 15,000 invested at 9.5% for five years will be:


Option 1: $ 22,125
Option 2: $ 16,625
Option 3: $ 23,614
Option 4: $ 26,250
Option 5: None of the above


The work breakdown structure, the work packages, and the company?s accounting system are tied together through the:


Option 1: Code of accounts
Option 2: Budgeting system
Option 3: Capital budgeting process
Option 4: Overhead rates
Option 5: All of the above


Life Cycle Costing:


Option 1: Is an activity devoted to optimizing cost/performance
Option 2: Is the concept of including all costs within the total life of a project.
Option 3: Is an activity of appraising the cost and technical performance of a completed project
Option 4: Is a process of predicting the life of a project
Option 5: All of the above


Which of the following are examples of indirect costs?


Option 1: Salaries of corporate executives
Option 2: Salaries of full-time project staff
Option 3: Overhead costs
Option 4: a and b
Option 5: a and c


Project Cost Management includes all of the following except:


Option 1: Resource leveling
Option 2: Resource planning
Option 3: Cost estimating
Option 4: Cost budgeting
Option 5: Cost control


Which of the following choices indicates that a project has a burn rate of 1.2


Option 1: The BCWS is 100 and the BCWP is 120.
Option 2: The ACWP is 100 and the BCWP is 120.
Option 3: The ACWP is 120 and the BCWP is 100.
Option 4: The BCWP is 100 and the BCWS is 120.
Option 5:


The inputs to Cost Budgeting includes all of the following except:


Option 1: Cost estimates
Option 2: Cost baseline
Option 3: WBS
Option 4: Project schedule
Option 5:


During the six month update on a 1 year, $50,000 project, the analysis shows that the BCWS is $25,000; the BCWP is $20,000 and the ACWP is $15,000. What can be determined from these figures?


Option 1: The project is behind schedule and over cost.
Option 2: The project is ahead of schedule and under cost.
Option 3: The project is ahead of schedule and over cost.
Option 4: The project is behind schedule and under cost.
Option 5:


Earned value is:


Option 1: Actual cost of work performed.
Option 2: Completed work value.
Option 3: Budgeted cost of work performed.
Option 4: Percent complete.
Option 5: All except A.


Which of the following statements concerning bottom-up estimating is true?


Option 1: The cost and accuracy of bottom-up estimating is driven by the size of the individual work items.
Option 2: Smaller work items increase both cost and accuracy.
Option 3: Larger work items increase both cost and accuracy.
Option 4: A and C
Option 5: A and B

Practice Free Cost Management Set 1 Questions online

By Practicing the below question set :
The student will get the basic and advanced knowledge on Cost Management Set 1.
The student will learned the priciples and methedology of Cost Management Set 1.
The student will evaluate the knowledge level on Cost Management Set 1.
Student can practice number of times the question till he is clear.
Student can provide the review / feedback / suggestion on the questions which will help to others.
The question contains the simple to complex level difficulties so that student can improve the knowledge.


Kindly Note : The information provided here is just indicative information and is provided on “as is” and “as available” basis . We make no claims on accuracy and reliability of the information. For correct/current information kindly contact concerned college/institution/authorities

Advertisements
Advertisements

Mail: Support@gicgac.com